Moscow
City International Business Center, Central
Core 180,000 m2
Employer:
GUP
Center City
Scope of Works:
MEP
and BMS System, Finishing Works
Project Start date:
01.03.2003
Project Finish
date:
01.04.2006
Scope
of Works
Mechanical
works
Supply and Installation of Heating System
Fire Fighting System (sprinkler and Fire hose cabinets)
Sanitary and Domestic water system Installations.
Ventilation system Installations 60,000 m2 Air Duct
Storm and Sewer Drain System
Electrical
works
10 kV Medium Voltage System (Transformer & Panels)
0,4 kV Main & Distribution Panel boards
MCC Panel boards and BMS System
Internal Lighting System
Power Distribution System
Fire Alarm System
Public Address and Announcement System
Telephone & Data System
Grounding & Lightning Protection System
Access Control System
CCTV System
Intrusion and Burglar Alarm System
Electric Time and Keeping System
Gas Alarm System
Automated Car Parking System